Current Stayton Projects

  • February 5, 2026 Update: 

    As part of the waterline improvement work along Shaff Road, around thirty house connections have been completed as of this afternoon and have been transferred to a new water distribution system. These homes, all located along Shaff Road (between N. Evergreen Ave and N. First Ave) may experience temporary dirty water in their home’s water distribution system.

    To resolve the potential dirty water issue, residents can turn on their cold water faucets for a period of five to ten minutes, until the water runs clear. We recommend that this flushing takes place before using the hot water system, to avoid dirt in hot water tanks. 

    Any visible dirt is most likely coming from internal plumbing, having been stopped and started, causing a water hammer effect. It is possible that filters in faucets may become blocked with dirt. If this is the case, removing and rinsing filters will resolve this issue. 

    The new main line system has been flushed and disinfected and it is very unlikely to have contaminated water. 

    If you have any questions, please contact Public Works at 503-769-2919.



    January 28, 2026 Project Update and Paving Timeline:


    As of today, all pipeline installation is complete. Over the next few weeks, the remaining construction work for this project will be wrapped up.

    Shaff Road will be paved once temperatures remain above 60 degrees for three days in a row. 

    For further information, please view our Why Wednesday video available on Facebook.

    *****

    Location: Shaff Road, from North First Avenue to Deer Avenue

    Estimated Completion: Extended through February 2026 (pavement restoration dependent on weather)

    Contractor: Civil West Construction

    Waterline improvement work is currently underway along Shaff Road, from North 1st Avenue to Deer Avenue. From Monday to Friday, flaggers will be present to manage alternating two-way traffic during construction hours. In addition, there is no access to Shaff Road from N. Douglas Avenue, N. Evergreen Avenue, and N. Fern Avenue during construction hours.

    Pedestrian access will remain open on the south side of Shaff Road.

    Shaff Road, N. Douglas Avenue, N. Evergreen Avenue, and N. Fern Avenue will be fully open outside construction hours and on weekends.

    Please expect delays. Thank you for your patience as we work to improve local infrastructure.

    For any questions, please contact Public Works at 503-769-2919.

Press the enter key or spacebar to expand or collapse the accordion

             Ida St. Paving Improvement Project        The Ida St. Paving Improvement project is now complete. This includes an upgraded waterline, 3 new fire hydrants, 10 ADA curb ramps, and an improved stepping curb. These improvements will continue to support the growing need for support and safety for the downtown area.

    The construction will be on E. Ida Street between N. 1st Avenue to N. 4th Avenue and will begin the first week of June 2024 and completed by the end of August 2024.

    We understand that residents day-to-day may be affected by construction. This may include:

    • Limited Parking
    • Limited Walkways
    • Limited Thru Streets

    That is why we are taking steps to connect with those that may be affected with:

    • Open communications
    • Up-to-date information

    Please check below to find updates, documents, and news regarding this project. You can send a comment or sign up to receive updates by email in the section below.

    For questions about the project, please contact Public Works Department at (503) 769-2919. 

    Project Updates
    Ida St. Paving Project Celebration
    09/01/2024

    Ida St. Improvement Project | Update as of June 16
    06/19/2024


    Ida Street Construction begins June 3rd
    05/31/2024

    Pacific Excavation will be performing construction along Ida Street starting at 1st Avenue and working along Ida Street to 4th Avenue, beginning the first week of June and is anticipated to be completed in 2 months. The Ida Street Improvement Project will be completed in phases, with traffic being impacted only on one block at a time until final paving.

     

    Traffic impacts will typically be limited to 2-3 business days per block, which may impact parking and thru traffic for those areas during working hours (7:00 AM to 6:00 PM). Local access will be maintained at all times for businesses and property owners, though there may be delays. As a reminder, there is a free public parking lot available on the corner of Florence Street and 2nd Avenue and by the Stayton Court House. Please be cautious of the construction crew and equipment when driving near the construction zone.

     

    Also, make sure to support your local businesses that may be affected by construction and respect private parking lots owned by other businesses near the construction zone.

     

    For additional information, contact Ian Kintz Stormo at (503) 769–2919 and stay up to date by visiting our Projects Page at www.staytonoregon.gov/page/pw_projects for updates.

     


    Ida St. Improvement construction will begin the first week of June
    05/10/2024

    The Ida Street Pavement & Waterline Improvement Project is scheduled to begin the first week of June. The contractor will have multiple crews working in different areas, starting with the waterline and storm system improvements. Traffic control plans will be reviewed and approved by Public Works employees to help limit the impact on businesses and residences.

     

    The contractor will post notices a minimum of 48-hours prior to water shutdowns or street closures. Local traffic access will be maintained throughout the project except for final paving scheduled mid-late July.

     

    For additional questions, please contact Stayton Public Works at (503) 768-2919.


    Resolution No. 1099 - Award Contract for Ida Street Improvement Project
    04/16/2024
    On April 15th, 2024 the Stayton City Council awarded the construction contract.  Construction has been scheduled to begin in the first week of June 2024. Construction zones and times will be provided at a later date.

    Documents
    • Email:required
      Confirm Email:
      Do you have a comment or question about Ida Street Improvement Project? Please send us your comments and questions here.

    Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

Upcoming Stayton Projects

  • The Mill Creek Park Project is a proposal started in 2019. The project will introduce new activities and elements for the community. Some examples include environmental improvements such as a fish mitigation passage and regional water facility. New structures and facilities like an observation tower, covered areas, and concessions stands. In addition, there will be new areas dedicated to recreational sports, gardening, and community-led events.

    The Mill Creek Park Master Plan below features two potential park layout and a detailed list of planned elements for each.

    We will continue to provide information about the project. Please stay tuned for further updates.

    Master Plan

Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion