Current Stayton Projects

             Ida St. Sanitary Sewer Replacement        The Ida St. Sanitary Sewer Replacement improve the wastewater infrastructure on West Ida St. to provide support and upgrades to growing needs in the area.

    Project Updates
    Comcast Update 4/18/24
    04/18/2024

    Comcast will request utility locates and will be placing signs in the neighborhood they will be working. The signs will be placed about 2 weeks prior to construction in that area.

     

    Comcast will provide door hanger notifications at least 48-hours before beginning work in the next neighborhood.

     

    Some of the work will be performed in easements on private property. The contractor will be required to restore landscaped areas affected by construction.

     

    If you have any issues please contact Fisk Communication at (360) 314-4454 or info@fiskcomm.com or Comcast Cable at (971) 777-0933 or at Phillip_Curtis@comcast.com.

     

    If you have any additional questions, please contact Public Works at 503-769-2919.


Press the enter key or spacebar to expand or collapse the accordion

  • Comcast will be installing new infrastructure throughout Stayton.

    Comcast has entered into a Franchise Utility Agreement with the City to install a new infrastructure throughout Stayton. The work is scheduled to begin in March 2024 and is anticipated to be completed by Spring 2025.

    Comcast will post signs, mark areas, and place door hangers notifying residents of upcoming construction in their neighborhood. Public Works will be meeting with local Comcast contractors on a regular basis to review construction plans and verify they are operating within the Oregon State Utility Notification Standards. To learn more about Oregon's Utility Notification Center and other applicable standards, please refer to the Oregon Utility Notification Center and the Updated Standards Manual.

    To learn more about Comcast's development in Oregon, please visit here: https://oregon.comcast.com/network/.

    If you have questions about Comcast's construction in Stayton, please contact Fisk Communication at (360) 314-4454 or info@fiskcomm.com or Comcast Cable at (971) 777-0933 or at Phillip_Curtis@comcast.com.

    If you have questions or concerns about the aerial (power pole) work, contact Darrel Talley with TexStar Enterprises at (971) 715-8151 or darrel.talley@texstarenterprises.com

    If you have any additional questions, please contact Public Works at 503-769-2919.

    Comcast Construction Updates

    Comcast Update 4/18/24
    04/18/2024

    Comcast will request utility locates and will be placing signs in the neighborhood they will be working. The signs will be placed about 2 weeks prior to construction in that area.

     

    Comcast will provide door hanger notifications at least 48-hours before beginning work in the next neighborhood.

     

    Some of the work will be performed in easements on private property. The contractor will be required to restore landscaped areas affected by construction.

     

    If you have any issues please contact Fisk Communication at (360) 314-4454 or info@fiskcomm.com or Comcast Cable at (971) 777-0933 or at Phillip_Curtis@comcast.com.

     

    If you have any additional questions, please contact Public Works at 503-769-2919.


    Comcast will be sending out advance notification of construction in Stayton with doorhangers and signboards. Examples have been provided below.

    Areas that have received notices may see contractors marking the area near the street with temporary spray paint and flags in preparation for construction in March. Contractors may also mark the area of the Public Utility Easement which may be parallel to or on private property.

    Below is a map of the estimated construction timeline.

    *NOTE: Map is subject to change and updates.

    Documents

    Frequently Asked Questions
    • Public Utility Easement (PUE) is a portion of land on private property that is dedicated to give utility companies the access to install and maintain infrastructure.

    Press the enter key or spacebar to expand or collapse the accordion

    • A franchise agreement is a contract that grants a franchise to operate on public and private property within a City under certain fees, rights, and rulings. As a provider of cable television service, Comcast is heavily regulated by federal, state, and local law. Primarily, under federal law, Comcast was required to obtain a franchise agreement with the City for use and operation of infrastructure within the City’s rights-of-way.

    Press the enter key or spacebar to expand or collapse the accordion

    • While the City has some authority to regulate Comcast through this franchise agreement, the federal Cable Act and Federal Communications Commission (FCC) regulations limit the City’s ability to regulate all aspects of Comcast’s service.  For example, the City is prohibited from unreasonably refusing to award a franchise to a franchise applicant. Given this strict federal regulatory context, this past year, the City negotiated a new franchise agreement with Comcast, establishing various terms and obligations regarding Comcast’s use and operation of its cable system within the City’s rights-of-way.

    Press the enter key or spacebar to expand or collapse the accordion

    • If you have questions or concerns about Comcast’s construction in Stayton, please reach out to Fisk Communication at (360) 314-4454 or info@fiskcomm.com

      To learn more Comcast FAQs, please visit here.

    Press the enter key or spacebar to expand or collapse the accordion

Press the enter key or spacebar to expand or collapse the accordion

             Ida St. Paving Improvement Project        The Ida St. Paving Improvement project is now complete. This includes an upgraded waterline, 3 new fire hydrants, 10 ADA curb ramps, and an improved stepping curb. These improvements will continue to support the growing need for support and safety for the downtown area.

    The construction will be on E. Ida Street between N. 1st Avenue to N. 4th Avenue and will begin the first week of June 2024 and completed by the end of August 2024.

    We understand that residents day-to-day may be affected by construction. This may include:

    • Limited Parking
    • Limited Walkways
    • Limited Thru Streets

    That is why we are taking steps to connect with those that may be affected with:

    • Open communications
    • Up-to-date information

    Please check below to find updates, documents, and news regarding this project. You can send a comment or sign up to receive updates by email in the section below.

    For questions about the project, please contact Public Works Department at (503) 769-2919. 

    Project Updates
    Comcast Update 4/18/24
    04/18/2024

    Comcast will request utility locates and will be placing signs in the neighborhood they will be working. The signs will be placed about 2 weeks prior to construction in that area.

     

    Comcast will provide door hanger notifications at least 48-hours before beginning work in the next neighborhood.

     

    Some of the work will be performed in easements on private property. The contractor will be required to restore landscaped areas affected by construction.

     

    If you have any issues please contact Fisk Communication at (360) 314-4454 or info@fiskcomm.com or Comcast Cable at (971) 777-0933 or at Phillip_Curtis@comcast.com.

     

    If you have any additional questions, please contact Public Works at 503-769-2919.


    Documents
    • Email:required
      Confirm Email:
      Do you have a comment or question about Ida Street Improvement Project? Please send us your comments and questions here.

    Press the enter key or spacebar to expand or collapse the accordion

    Comcast Update 4/18/24
    04/18/2024

    Comcast will request utility locates and will be placing signs in the neighborhood they will be working. The signs will be placed about 2 weeks prior to construction in that area.

     

    Comcast will provide door hanger notifications at least 48-hours before beginning work in the next neighborhood.

     

    Some of the work will be performed in easements on private property. The contractor will be required to restore landscaped areas affected by construction.

     

    If you have any issues please contact Fisk Communication at (360) 314-4454 or info@fiskcomm.com or Comcast Cable at (971) 777-0933 or at Phillip_Curtis@comcast.com.

     

    If you have any additional questions, please contact Public Works at 503-769-2919.


Press the enter key or spacebar to expand or collapse the accordion

Upcoming Stayton Projects

  • The Mill Creek Park Project is a proposal started in 2019. The project will introduce new activities and elements for the community. Some examples include environmental improvements such as a fish mitigation passage and regional water facility. New structures and facilities like an observation tower, covered areas, and concessions stands. In addition, there will be new areas dedicated to recreational sports, gardening, and community-led events.

    The Mill Creek Park Master Plan below features two potential park layout and a detailed list of planned elements for each.

    We will continue to provide information about the project. Please stay tuned for further updates.

    Master Plan